Site clearing activities are scheduled to ramp up with the number of trucks hauling trees to Minette Bay load-out facility increasing to 5 per day from March 6 and then 7 per day from March 11. The trucks will move between the project site and Minette Bay between 7:00 am and 5:30 pm, 6 days a week – Monday to Saturday.
Quick Navigation
JFJV in the Community
Social Media
JFJV Kitimat1 day ago
As we focus on commissioning activities and supporting LNG Canada in achieving the export of first cargo to global markets, we are truly proud of the remarkable progress of Team JFJV Kitimat and our many contractors and subcontractors.
Check out our Q1 2025 site update video!
Check out our Q1 2025 site update video!

JFJV Kitimat3 weeks ago
The Maran Gas Roxana safely arrived carrying a cargo of liquefied natural gas that will be offloaded into the LNG Canada facility for equipment testing. This activity is critical to the safe start-up and commissioning process in advance of normal operations