Work is now underway to construct the LNG Canada Project Materials Offloading Facility (MOF), which is located between Rio Tinto’s Terminal B and the former Methanex causeway.

As part of this work, piling will occur intermittently between 7 a.m. and 10 p.m.—seven days per week—and is expected to be complete in February/March 2020. The piles will primarily be installed using vibratory method. Area residents may hear limited noise from the activity.

Once complete, the MOF will be used to unload the LNG processing modules, which will still start being delivered to site via marine transport in summer 2021.