Construction Updates

Update on site clearing activities

Site clearing activities are scheduled to ramp up with the number of trucks hauling trees to Minette Bay load-out facility increasing to 5 per day from March 6...


Posted By Comments: 0 0Post Date: March 4, 2019

Site clearing activities resume

Site clearing activities resume on January 3 with air curtain burning of non-merchantable timber logs. Air curtain burning is an effective and environmentally friendly method of eliminating wood...


Posted By Comments: 0 0Post Date: January 3, 2019

Geotechnical services concluded

The first round of geotechnical services has been concluded. This process covered analyses for both surface and subsurface exploration of the site, assessing how earth materials will interact...


Posted By Comments: 0 0Post Date: December 21, 2018

Site clearance begins on JFJV project site

Site clearing activities commenced on December 5, 2018 on the JFJV project site. These activities are being carried out by Haisla Brinkman JV. They will be on site...


Posted By Comments: 0 0Post Date: December 7, 2018

JFJV mobilizes to site

JGC-Fluor (JFJV) officially mobilized to site, taking over 2 of the 4 construction areas. With this move, on-site activities are scheduled to ramp up with the geo-technical and...


Posted By Comments: 0 0Post Date: November 19, 2018