Construction Updates

Incident at Kitimat River Water Intake (RWI) construction site

Kitimat, B.C. - At 5:30pm (PST) on May 30, 2020, a hydraulic oil spill occurred at the Kitimat River Water Intake (RWI) construction site. 100ml (the equivalent of...


Posted By Comments: 0 0Post Date: May 31, 2020

Work in Kitimat River begins May 20

Today, work will begin in the Kitimat River to refurbish an existing in-water intake for the LNG Canada Project.As part of the LNG Canada plant design, water will...


Posted By Comments: 0 0Post Date: May 20, 2020

River Water Intake (RWI) Pumphouse Project Update

Further to our notification issued on March 11, 2020, regarding construction of new river water pumphouse begins this spring, we would like to provide you with a number...


Posted By Comments: 0 0Post Date: May 5, 2020

Testing of back-up generators for LNG Canada Project now underway

JGC Fluor is currently testing several back-up diesel generators for Cedar Valley Lodge. Visible plumes of exhaust can be expected. This is normal for generators of this size...


Posted By Comments: 0 0Post Date: April 30, 2020

Night-time vibratory piling at Materials Offloading Facility begins week of April 13

Work is well underway to construct the LNG Canada Project Materials Offloading Facility (MOF), which is located between Rio Tinto’s Terminal B and the former Methanex causeway. As...


Posted By Comments: 0 0Post Date: April 14, 2020

Project Resource Centre closed indefinitely

Due to the COVID-19 pandemic, the JGC Fluor Project Resource Centre in City Centre, Kitimat is closed until further notice.If you need to contact us, you can by...


Posted By Comments: 0 0

Construction of new river water pumphouse begins this spring

This spring, construction of a new river water pumphouse for the LNG Canada Project will begin.As part of the LNG processing plant design, water will be sourced from...


Posted By Comments: 0 0Post Date: March 11, 2020

Site preparation for new river water pumphouse and water line to begin week of February 10

Beginning the week of February 10, site preparation activities (tree felling, clearing, and grubbing) will begin for construction of a new river water pumphouse, water line, and substation...


Posted By Comments: 0 0Post Date: February 10, 2020

JGC Fluor’s piling program continues in 2020

Work on the LNG Canada Project is well underway and JGC Fluor will continue to ramp up construction activities in 2020, including piling throughout the project site. Piles...


Posted By Comments: 0 0Post Date: January 22, 2020

Intermittent traffic delays at Alcan Bridge begin week of Jan. 13, 2020

Starting as early as January 14, work will continue for the twinning of Alcan Bridge. Crews successfully lifted the new bridge structure into place on January 10 and...


Posted By Comments: 0 0Post Date: January 13, 2020