Testing of back-up generators for LNG Canada Project now underway

JGC Fluor is currently testing several back-up diesel generators for Cedar Valley Lodge. Visible plumes of exhaust can be expected. This is normal for generators of this size...


Posted By Comments: 0 0Post Date: April 30, 2020

National Day of Mourning – April 28, 2020

On this National Day of Mourning, we remember those who died from workplace injuries and illnesses across B.C. and Canada, and recommit to being Safer Together. We will...


Posted By Comments: 0 0Post Date: April 28, 2020

JGC Fluor submission – Canadian Navigable Waters Act

JGC Fluor BC LNG Joint Venture (“JFJV”) hereby gives notice that a submission has been added to the Navigable Waters Registry pursuant to the Canadian Navigable Waters Act...


Posted By Comments: 0 0Post Date: April 20, 2020

Night-time vibratory piling at Materials Offloading Facility begins week of April 13

Work is well underway to construct the LNG Canada Project Materials Offloading Facility (MOF), which is located between Rio Tinto’s Terminal B and the former Methanex causeway. As...


Posted By Comments: 0 0Post Date: April 14, 2020

COVID-19 Response Update #6

LNG Canada and JGC Fluor (JFJV) continue to implement important measures to help reduce the spread of the COVID-19 virus. As outlined in our previous COVID-19 Response updates,...


Posted By Comments: 0 0Post Date: April 9, 2020

COVID-19 Response Update #5

LNG Canada and JGC Fluor continue to implement important measures to help reduce the spread of the COVID-19 virus. As outlined in our previous COVID-19 Response updates, we’re...